Piles Drilled, Filled At 1221 West Washington Residential Tower

1221 West Washington construction updateThe giant auger at 1221 West Washington Boulevard.

Auger cast piles are in full effect at the 1221 West Washington residential tower where the Fulton Market District meets the West Loop. Michels Construction has a giant corkscrew at the construction site that has been drilling shafts into the earth, to be filled in with concrete and then a rebar cage.

Focus, DAC Developments, and Melrose Ascension Capital are putting up a 19-story, 287-unit apartment tower following the demolition of the historic D.H. Burnham-designed Chicago Machinery Exchange Building at 1217-1227 West Washington back in 2018. Designed by Pappageorge Haymes Partners, the new tower will include 183 parking spaces within a brick-clad four-story podium, with 3,000 square feet of retail at ground level.

1221 West Washington construction progress

Chicago Machinery Exchange Building, built in 1910, demolished in 2018. Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

1221 West Washington construction update

Rebar cages wait to be sunk into concrete shafts. Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

1221 West Washington construction update

Rebar cages wait beside the auger. Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

1221 West Washington construction update

Photo by Daniel Schell

The foundation permit for 1221 West Washington was issued in December 2022. A pair of reinstatement permits came next in 2023, but the site remained idle until things got real again when the full permit came through on May 16 of this year. The tower crane was permitted in early October. Focus is the general contractor, with McHugh Concrete as the concrete contractor.

1221 West Washington full building permittted

Rendering of 1221 West Washington via Pappageorge Haymes Partners.

1221 West Washington excavation work

1221 West Washington by Pappageorge Haymes Partners.

1221 West Washington excavation work

1221 West Washington by Pappageorge Haymes Partners.

1221 West Washington construction update

Building section diagram, via Chicago Plan Commission presentation.

1221 West Washington construction update

Ground floor plan, via Chicago Plan Commission presentation.

1221 West Washington construction update

Second-fourth floor parking plans, via Chicago Plan Commission presentation.

1221 West Washington construction update

Residential demising plan, via Chicago Plan Commission presentation.

1221 West Washington construction update

Amenity floors, via Chicago Plan Commission presentation.

1221 West Washington construction update

Roof plan, via Chicago Plan Commission presentation.

Apartments will range in size from 430 to 804 square feet, and include studio, convertible, one-bedroom, and two-bedroom floor plans. Amenities will feature a rooftop pool and grill stations, a spa with steam room and sauna, a fitness center, and a dog run. Focus plans to welcome the first tenants in 2027.

Subscribe to YIMBY’s daily e-mail

Follow YIMBYgram for real-time photo updates
Like YIMBY on Facebook
Follow YIMBY’s Twitter for the latest in YIMBYnews

.

7 Comments on "Piles Drilled, Filled At 1221 West Washington Residential Tower"

  1. WAY too much parking, ugh

  2. A Steam Room is going to be a very expensive amenity as it gobbles up electricity .

    And it will be high maintenance going forward .

  3. It would’ve been amazing if that facade was saved and the tower built behind it