Exterior glass has reached halfway up the sides of the apartment tower at 220 North Ada in the West Loop. The 29-story, 308-unit development is expected to welcome tenants in early 2026.
General contractor Clayco closed out 2024 by getting a permit to install three passenger elevators on New Year’s Day.

Glass on the south and west façades, shot from Randolph Street on 02/25/2025. Photo by Daniel Schell

Photo by Daniel Schell

Photo by Daniel Schell

Mind the gap. Photo by Daniel Schell

Looking north up Ada Street. Photo by Daniel Schell

South and east facades. Photo by Daniel Schell

Photo by Daniel Schell

South and east façades from Elizabeth Street. Photo by Daniel Schell

Looking west from Elizabeth Street. Photo by Daniel Schell

Photo by Daniel Schell

East and north façades. Photo by Daniel Schell

Glass progress on 02/03/2025. Photo by Daniel Schell

Glass progress on 02/03/2025. Photo by Daniel Schell

Glass progress on 01/11/2025. Some of this glass was removed and replaced, as seen in the two previous photos from Feb 3.

Glass progress on 01/11/2025. Photo by Daniel Schell
Subscribe to YIMBY’s daily e-mail
Follow YIMBYgram for real-time photo updates
Like YIMBY on Facebook
Follow YIMBY’s Twitter for the latest in YIMBYnews
Bulky! The infill in that end of the WL shares a common drabness. Together they amount to a bittersweet symphony!